For OEM engineers and buyers in North America, Europe and Australia who are collecting sheet metal fabrication quotes from China.

Guide to writing a sheet metal RFQ and comparing sheet metal fabrication quotes from China

Figure 1. One drawing, three quotes: the gaps in an RFQ decide how far the prices drift apart.

Contents

  1. 1.Quick Answer
  2. 2.Complete RFQ Package
  3. 3.Details That Raise the Price
  4. 4.How a Quote Is Built
  5. 5.Compare Quotes Apples to Apples
  6. 6.Reading the Fine Print
  7. 7.Questions Before You Accept
  8. 8.Red Flags in a Quotation
  9. 9.When the Lowest Quote Costs More
  10. 10.How STARWAY Handles RFQs
  11. 11.Conclusion
  12. 12.FAQs

You send the same enclosure drawing to three fabricators. The first sheet metal fabrication quote comes back with a tidy unit price. The second is nearly double. The third adds a tooling charge the other two never mentioned. Which one is right?

Often all three are, for the job each of them imagined. Every shop filled the gaps in your RFQ with its own assumptions: a different material grade, a different coating spec, more or less inspection, different packing, a different delivery term. Before the numbers mean anything, you have to get everyone pricing the same part.

This guide covers both halves of that work. First, how to write a sheet metal RFQ that gets comparable answers. Then, how to read, normalize and question the quotes that come back. Still building your shortlist? Start with our guide on how to evaluate and qualify a sheet metal fabrication supplier in China.

I’ve read a lot of RFQs from the fabricator’s side of the table. The quotes that cause trouble later are rarely the high ones. They’re the ones built on a guess. At STARWAY MFG GROUP, our sheet metal fabrication engineers send DFM questions with the quotation, so the assumptions are written down before anyone compares prices.


Quick Answer: Why Do Sheet Metal Quotes Vary So Much?

Because every RFQ leaves something open, and each shop fills the gap differently. The supplier with the most questions often isn’t the most expensive one. It’s the one that noticed what you didn’t specify. To get quotes you can actually compare:


What a Complete Sheet Metal RFQ Package Includes

RFQ stands for request for quotation. For a fabricated part, though, it’s really a request for a process plan. The shop can only price what it can see. Anything you leave out, it will guess.

RFQ item Why it changes the price What happens if it’s missing
2D drawing + 3D model (STEP) Defines the flat pattern, bend count and hole features The shop redraws or guesses features; revision mix-ups
Drawing revision level Ties every quote to one design Quotes from different revisions end up side by side
Material grade and thickness Raw material is often the largest single cost line “Stainless” quoted as 304 by one shop and 316 by another
Finish spec (type, color, texture, masking) Coating, plating and masking add steps and batches Powder coat, wet paint and zinc plating mixed in one comparison
Critical dimensions and inspection needs Drives fixtures, inspection time and reports Every tolerance priced as if it were critical
Hardware (PEM nuts, studs, standoffs) Part numbers, purchasing and insertion labor Generic hardware substituted without asking
Annual volume and first batch size Sets setup amortization and the process route Prototype pricing used for production, or the reverse
Packing spec and Incoterm Export packing, protection and freight scope An EXW price compared with a DDP price

Put all of this in one PDF or a short spec sheet. Don’t scatter it across six emails. If the part is an assembly, attach the BOM and say which items you’ll supply and which the fabricator should buy.

Checklist of documents and details to include in a sheet metal fabrication RFQ

Figure 2. The eight items that make an RFQ package quotable.


RFQ Details That Raise the Price Most

Some lines on a drawing cost far more than they look. Check these before the RFQ goes out.

Engineer reviewing a 3D CAD model and measuring key features before preparing a quote

Figure 3. Reviewing the 3D model and checking key features before the quote is prepared.

Tight tolerances applied to everything

A title-block tolerance of ±0.1 mm on a 600 mm bent panel tells the shop that every dimension is critical. So they price extra inspection, slower bending and some scrap. Keep tight tolerances on the features that mate with something. Let the rest follow a general tolerance standard such as ISO 2768. (These figures are typical industry examples, not a STARWAY specification.)

Tolerances after welding or coating

Is the dimension checked before powder coating or after? Before welding or after? A post-weld flatness callout on a large frame can mean dedicated fixtures, straightening and extra checks. Say which state the tolerance applies to, or two suppliers will quote two different jobs.

Cosmetic surfaces

“No scratches” on every face means protective film, gloves, separators and slower handling. Mark which faces are cosmetic. Otherwise one shop protects everything and charges for it, and another protects nothing.

A single quantity

Ask for two or three tiers, say a prototype lot, a first batch and your annual run rate. Laser programming, press-brake setup and fixtures get spread across the batch, so the unit price drops as quantity rises. One tier hides that curve.


How Fabricators Build a Sheet Metal Fabrication Quote

Most fabricators build a sheet metal fabrication quote from the same blocks. Know the blocks and you know what to ask for, and what’s missing when a quote looks thin.

Cost element What drives it How the buyer can influence it
Material Grade, thickness, nesting yield, market price Use standard grades and gauges; avoid shapes that nest poorly
Cutting Cut length, pierce count, thickness Remove non-functional cutouts and tiny features
Bending and forming Number of bends, tool changes, part size Standardize bend radii; avoid bends that need special tooling
Welding and grinding Weld length, fixtures, cosmetic grinding Use tabs or hardware where welds aren’t structural; define the weld finish you need
Hardware insertion Number and type of PEM fasteners Consolidate sizes; specify hardware only where it’s needed
Finishing Coating type, masking, color changes, batch size Use standard colors; minimize masked areas
Inspection and documents FAI, dimensional reports, sampling level Tie report scope to the critical features
Packing and logistics Export packing, surface protection, Incoterm Agree on a packing spec before the quote
NRE, fixtures and tooling One-time fixtures, special punches, programming Ask for it as a separate line

*Cost drivers are general industry observations, not STARWAY pricing. Actual quotes depend on the part, quantity and specifications and are for reference only.

On a simple flat bracket, material can be most of the price. On a welded, coated enclosure with twenty PEM nuts, labor and finishing take over. That’s why no single percentage rule fits every part, and why you want the breakdown rather than one number.

Breakdown of the cost elements that make up a sheet metal fabrication quote

Figure 4. Typical cost elements in a sheet metal quote. Shares vary by part; no prices implied.


How to Compare Sheet Metal Quotes Apples to Apples

Once the quotes are in, put them in one spreadsheet. Then make them comparable, line by line:

Line item Supplier A Supplier B Supplier C
Drawing revision quoted Rev C Rev C Rev B ⚠
Material 304 2B, 1.5 mm 304 2B, 1.5 mm “Stainless” ⚠
Finish Powder coat, RAL 9005, texture Powder coat, RAL 9005, texture Not included ⚠
NRE / fixtures Listed separately Included in unit price Not mentioned ⚠
Inspection report FAI + critical dimensions FAI Not stated ⚠
Packing Export carton + pallet Export carton + pallet Standard carton
Incoterm FOB Shanghai EXW DDP
Quote validity 30 days 15 days Not stated

Supplier C may well show the lowest number. Look at the gaps, though. Old revision, no finish, no NRE line. That’s not a lower price for your part. It’s a price for a different part.

Template for comparing sheet metal fabrication quotes from three suppliers side by side

Figure 5. Normalize revision, scope, NRE and delivery term before ranking quotes.

EXW, FOB or DDP?

Under the Incoterms® rules published by the ICC, EXW means you take over at the factory door: export clearance, trucking, ocean or air freight, import duties. FOB means the supplier clears the goods for export and loads them at the named port. DDP means the supplier delivers to your address with duties paid. A DDP quote will always look higher than an EXW quote for the same part. Convert everything to one term, or better, to your landed cost, before you rank anyone.

Comparison of EXW, FOB and DDP terms for the landed cost of sheet metal parts

Figure 6. Where cost and responsibility pass to the buyer under EXW, FOB and DDP.


Reading the Fine Print in a Quotation

The conditions under the price table matter as much as the price. Look for:

None of these is a problem on its own. The problem is finding out about them after the PO is signed.


Questions to Send Back Before You Accept a Quote

Copy these into your reply to each shortlisted supplier. Their answers fill the holes the quote left.

  1. Which drawing revision, material grade and thickness did you quote?
  2. Which finish spec is included, and are masked areas priced?
  3. Which dimensions will you inspect, and what report will we receive?
  4. Is any NRE, fixture or programming cost included in the unit price?
  5. At what quantity does the unit price change?
  6. Which Incoterm and packing spec does this price assume?
  7. Which operations are subcontracted, for example plating or powder coating?
  8. How long is the quote valid, and what would trigger a price change?
  9. When does the lead time start, and does it include finishing?
  10. How are engineering changes after the PO priced?
  11. Did you find any DFM issues that would change this price?

Red Flags in a Sheet Metal Quotation

These are about the quote itself. For warning signs about the supplier, such as capability gaps or a quality system that only exists on paper, see our guide on how to evaluate and qualify a sheet metal supplier in China.


When the Lowest Quote Becomes the Most Expensive

A low sheet metal fabrication quote can turn into the expensive option once the parts land. The costs just show up somewhere else:

So add a line for risk when you compare. A supplier that writes its assumptions down up front usually costs less over a program than one that’s cheap on paper.

Inspectors checking a welded aluminum sheet metal enclosure against the drawing before shipment

Figure 7. Checking a welded aluminum enclosure against the drawing before shipment.


How STARWAY MFG GROUP Handles RFQs

At STARWAY MFG GROUP, our approach is to review the drawing before we price it. If a feature looks hard to form, a tolerance is unclear or the finish note is open, we ask, or we write the assumption into the quotation so you can see it. Comments on manufacturability come back with the quote through our design and engineering support.

Our Nantong Flexible Manufacturing Base holds ISO 9001:2015 certification for the processing of sheet metal parts. The work behind a typical quote runs through laser cutting, CNC bending, sheet metal welding, finishing and assembly. For new designs, rapid prototyping lets you check fit before you commit to a production quote. Our quality control information explains the inspection stages you can ask about.


Conclusion: Compare the Assumptions, Then the Price

A sheet metal fabrication quote is only as good as the RFQ behind it. Send one complete package. Ask for a breakdown. Bring every quote to the same revision, quantity and delivery term, and read the conditions before you rank anyone. The lowest number on your spreadsheet is a good place to start asking questions. It’s a poor place to stop.

Want to see how your part would be routed and priced? Explore STARWAY’s sheet metal fabrication services, or send us your drawing.

Have a drawing ready?

Request a DFM Review and Quotation


Frequently Asked Questions

Latest information
Return

This website uses cookies to provide you with a personalized browsing experience and analyze website traffic. By clicking "Accept", you agree to our use of cookies.